Example: A Site about Examples
Government Approved Demolition Contractor
Industrial demolition · Whitefield
Completed projectSubcontract4 factory sheds

Old Factory Sheds at Shreno Limited Demolition & Internal Alterations

We completed 1,20,000 sq ft of demolition and dismantling work at Alembic City, Whitefield: full demolition of two factory sheds and internal alterations in two more. Working as subcontractor to engineer Amarnath, we finished the job in five months.

Factory shed demolition and dismantling project covering 1,20,000 sq ft at Shreno Limited, Whitefield
Completed projectWhitefield · Bengaluru
Total work area
1,20,000 sq ft
Fully demolished
2 sheds
Internal alterations
2 sheds
Time taken
5 months
Overview

Project overview

The project involved old factory sheds at Shreno Limited Colony in Alembic City. The total demolition and dismantling area was 1,20,000 sq ft.

We used one excavator and more than 25 experienced workers for the demolition, dismantling and material handling.

Scope of work

  • Full demolition and dismantling of two factory sheds.
  • Internal alterations in two more sheds.
  • Recovery and sorting of dismantled materials.
  • Recovered materials taken by BCM Demolition Group.
Our role

Working as demolition subcontractor

BCM Demolition Group was appointed as subcontractor by engineer Amarnath. The job combined full demolition of two sheds with internal alterations in two others.

Shed 1Fully demolished
Shed 2Fully demolished
Shed 3Internal alterations
Shed 4Internal alterations

2 sheds fully demolished + 2 sheds internally altered = 1,20,000 sq ft of demolition and dismantling work.

Method

How the work was done

One excavator and more than 25 experienced workers handled the demolition, dismantling, internal alterations and recovered materials.

Equipment 1 excavator
  • 1 × Tata Hitachi ZX-200 Prime
Workforce 25+ experienced workers

Dismantling, alterations and material handling.

  1. Mobilisation

    Excavator and workers brought to site.

  2. Shed demolition

    Two sheds demolished and dismantled completely.

  3. Internal alterations

    Alteration work carried out inside the other two sheds.

  4. Material recovery

    Recovered materials sorted and taken by BCM.

Result

Completed in 5 months

We completed the full 1,20,000 sq ft of demolition and dismantling work in five months, with no major problems reported.

BCM Demolition Group took all recovered materials as part of the project arrangement.

Work completed

What was done

2 shedsFully demolished
2 shedsInternally altered
MaterialsRecovered, sorted, taken by BCM
Videos

Site videos

Footage from our work at Shreno Limited, Whitefield.

Animated footage of industrial demolition work by BCM Demolition Group at Shreno Limited

01Shed demolition

Footage from the factory shed demolition.

Animated footage of factory shed dismantling by BCM Demolition Group at Shreno Limited

02Shed dismantling

Another view of the dismantling work on site.

FAQs

Common questions

What work was done at Shreno Limited?

Full demolition and dismantling of two old factory sheds and internal alterations in two more sheds, covering 1,20,000 sq ft in total, at Alembic City, Whitefield.

Was BCM the main contractor?

No. BCM Demolition Group worked as demolition subcontractor, appointed by engineer Amarnath.

What equipment and workforce were used?

One Tata Hitachi ZX-200 Prime excavator and more than 25 experienced workers.

How long did it take?

Five months, with no major problems reported.

Who kept the recovered materials?

BCM Demolition Group took all recovered materials as part of the project arrangement.

error: Content is protected !!
Scroll to Top