Old Safety Lab RCC building demolition project at Exide Energy Solutions in Bengaluru Rural
Industrial demolition project · Exide Energy Solutions · Bengaluru Rural
BCM Demolition Group · Project case study

Old Safety Lab BuildingDemolition at Exide Energy Solutions

Demolition of a 37,000 sq ft single-storey RCC building at Exide Energy Solutions in Polanahalli, Bengaluru Rural. BCM’s 45-day scope covered MS barricading, structural demolition, foundation removal, material recovery and debris clearance.

Structure area
37,000 sq ft
Completion time
45 days
Approximate height
25 ft
Workforce
15+ workers
01 · Project overview

RCC demolition within an operating battery plant

BCM Demolition Group carried out the demolition of the Old Safety Lab building for Exide Energy Solutions. The single-storey reinforced cement concrete structure covered approximately 37,000 sq ft and stood about 25 feet high.

The surrounding battery plant was operational, making separation of the demolition area and attention to nearby activities central to the work.

Scope of work

  • MS barricading around the demolition work area.
  • Mechanical demolition of the RCC superstructure.
  • Removal of the building foundations.
  • Recovery and segregation of dismantled materials.
  • Removal of demolition debris and site clearance.
02 · Method & equipment

Mechanical demolition and foundation removal

Two Tata Hitachi ZX-220 LC excavators and a workforce of more than 15 workers were deployed for demolition, material handling and clearance.

2 × Tata HitachiZX-220 LC excavators
15+ workersDemolition support and material handling

Work sequence

  1. Barricade the demolition area with MS barriers.
  2. Carry out mechanical demolition of the RCC building.
  3. Remove foundations and segregate recovered materials.
  4. Load and remove demolition debris to clear the work area.
03 · Project challenges

Working beside an operational battery plant

The main challenge was carrying out heavy concrete demolition within a running battery plant. The work required particular attention to the boundary between the demolition zone and surrounding plant activities.

MS barricading formed part of BCM’s scope to separate the work area. The two excavators handled the heavy RCC demolition and foundation removal, supported by the site workforce.

04 · Completion & material recovery

A 45-day demolition and clearance scope

BCM completed the building demolition, foundation removal and debris clearance over 45 days.

Recovered materials were taken by BCM Demolition Group as part of the project scope.

05 · From the site

Barricading the demolition area

Animated site footage of MS barricading for BCM Demolition Group’s Exide demolition project
Site footage showing the barricading of the demolition work area at Exide Energy Solutions.
06 · Project record

Project work order

Work order supplied for this project. Tap the image to view the full-size document.

Exide Energy Solutions work order for BCM Demolition Group
Exide Energy Solutions · Work Order for BCM Demolition Group