Completed projectDirect clientFinished in 27 days

Devi Kiran Old Factory Demolition & Dismantling

We demolished, dismantled and cleared a 76,000 sq ft old paper mill factory in Bengaluru in just 27 days, within the client’s one-month deadline.

Devi Kiran Paper Mills factory demolition and dismantling project in Kumbalgodu, Bengaluru
Completed projectKumbalgodu · Bengaluru
Total area
76,000 sq ft
Time taken
27 days
Height (approx.)
35–40 ft
Workforce
25+ workers
Overview

Project overview

The Devi Kiran Paper Mills site had two types of structure: 28,000 sq ft of RCC construction and 48,000 sq ft of sheet-roofed sheds. We used both manual and mechanical methods to complete the work.

RCC structure 28,000 sq ft Sheet-roofed sheds 48,000 sq ft

Scope of work

  • Dismantling of the sheet-roofed shed structure.
  • Demolition of the RCC factory structure.
  • Sorting and recovery of reusable and recyclable materials.
  • Removal of debris and remaining waste.
  • Final site clearance and handover.
Method

How the work was done

Our workers handled the manual dismantling, while the excavators handled the demolition and debris clearance.

Equipment 3 excavators
  • 3 × Tata Hitachi ZX-200 LC
Workforce 25+ workers

Manual dismantling and site support.

  1. Mobilisation

    Workers and machines brought to site.

  2. Dismantling & demolition

    Sheds dismantled by hand and the RCC structure demolished by machine.

  3. Sorting & debris removal

    Recovered materials sorted and debris removed.

  4. Clearance & handover

    Final site clearance and handover to the client.

Deadline

One-month deadline. Done in 27 days.

The client needed the demolition, dismantling and clearance finished within one month. We put more than 25 workers and three excavators on the 76,000 sq ft site.

27 daysDeadline: 1 month
Finished before the deadline

Completed in 27 days

MaterialsRecovered and sorted for recycling
WasteRemoved from site
SiteCleared and handed over
Video

Site video

Footage from the Devi Kiran factory demolition and dismantling.

Animated footage of Devi Kiran factory demolition by BCM Demolition Group

01Factory demolition in progress

On-site footage from the Devi Kiran Paper Mills project.

Certificate

Work completion certificate

A work completion certificate was supplied for this project. Tap the image to see the full-size document.

Project
Devi Kiran Old Factory
Document
Work Completion Certificate
Contractor
BCM Demolition Group
Work completion certificate for BCM Demolition Group’s Devi Kiran old factory demolition project View full size
Devi Kiran Old Factory · Work Completion Certificate
FAQs

Common questions

What was demolished at Devi Kiran Paper Mills?

An old paper mill factory of 76,000 sq ft: 28,000 sq ft of RCC construction and 48,000 sq ft of sheet-roofed sheds, about 35–40 ft high.

How long did it take?

27 days, within the client’s one-month deadline. This included demolition, dismantling, material recovery, waste removal and final site clearance.

What equipment and workforce were used?

Three Tata Hitachi ZX-200 LC excavators and more than 25 workers, using both manual dismantling and mechanical demolition.

What happened to the materials?

Reusable and recyclable materials were recovered and sorted for recycling. Debris and remaining waste were removed before the site was handed over.

Is there a completion certificate?

Yes. A work completion certificate for the Devi Kiran Old Factory project is shown on this page.