Old Safety Lab Building Demolition at Exide Energy Solutions
We demolished a 37,000 sq ft single-storey RCC building inside Exide Energy Solutions’ running battery plant in Polanahalli, Bengaluru Rural. The 45-day job covered MS barricading, demolition, foundation removal, material recovery and debris clearance.
- Area
- 37,000 sq ft
- Time taken
- 45 days
- Height (approx.)
- 25 ft
- Workforce
- 15+ workers
Project overview
We demolished the Old Safety Lab building for Exide Energy Solutions. It was a single-storey RCC structure of about 37,000 sq ft and around 25 ft high.
The battery plant around it was still running, so keeping the demolition area separate and working carefully near plant activities were key.
Scope of work
- MS barricading around the work area.
- Mechanical demolition of the RCC building.
- Removal of the building foundations.
- Recovery and sorting of materials.
- Debris removal and site clearance.
How the work was done
Two excavators and more than 15 workers handled the demolition, material handling and clearance.
- 2 × Tata Hitachi ZX-220 LC
Demolition support and material handling.
Barricading
Work area closed off with MS barriers.
Demolition
The RCC building demolished by machine.
Foundations & sorting
Foundations removed and recovered materials sorted.
Debris clearance
Debris loaded and removed to clear the work area.
Working inside a running battery plant
The main challenge was heavy concrete demolition while the battery plant around it kept working. Keeping a clear boundary between the demolition zone and plant activities was essential.
Plant kept running
Work was done right next to ongoing battery plant activities.
MS barricading
Barriers separated the demolition area from the rest of the plant.
Heavy RCC work
Two excavators handled the RCC demolition and foundation removal, supported by the site team.
Completed in 45 days
We completed the building demolition, foundation removal and debris clearance in 45 days.
BCM Demolition Group took the recovered materials as part of the project scope.
Work area clearedWhat was removed
Site video
Barricading the demolition area at Exide Energy Solutions.

01Barricading the work area
MS barriers being put up around the demolition area.
Project work order
The work order for this project is shown here. Tap the image to see the full-size document.
- Client
- Exide Energy Solutions
- Document
- Work Order
- Contractor
- BCM Demolition Group
View full size
Common questions
What was demolished at Exide Energy Solutions?
The Old Safety Lab building, a single-storey RCC structure of about 37,000 sq ft and around 25 ft high, in Polanahalli, Devanahalli Taluk, Bengaluru Rural.
How was the work done inside a running plant?
MS barricading separated the demolition area from the rest of the battery plant, and the team worked with close attention to nearby plant activities.
What equipment and workforce were used?
Two Tata Hitachi ZX-220 LC excavators and more than 15 workers.
How long did it take?
45 days, covering the barricading, demolition, foundation removal and debris clearance.
Who kept the recovered materials?
BCM Demolition Group took the recovered materials as part of the project scope.