We demolished 27 unfinished RCC villas near Devanahalli International Airport, with a combined built-up area of 63,000 sq ft. Working as subcontractor to Uday Kumar, we completed the demolition, foundation removal and debris clearance in 4 months.

27 unfinished RCC residential villas demolition project by BCM Demolition Group near Devanahalli International Airport
Completed projectDodjala · near Devanahalli Airport
Villas
27 villas
Built-up area
63,000 sq ft
Time taken
4 months
Workforce
40+ workers
Overview

Project overview

The project covered 27 unfinished RCC villas at Dodjala, near Devanahalli International Airport. Together they had a built-up area of about 63,000 sq ft.

Our work included demolishing the standing structures, removing the foundations, clearing the debris and taking the recovered materials.

Scope of work

  • Full demolition of all 27 unfinished RCC villas.
  • Removal of the villa foundations.
  • Recovery and sorting of demolition materials.
  • Loading and removal of debris.
  • Clearing the work areas.
Our role

Working as demolition subcontractor

Uday Kumar won the demolition work from Ideal Pro and appointed BCM Demolition Group to carry out the full demolition scope.

Support for a large project

For this large project, BCM supplied 4 excavators and more than 40 workers. We carried out the demolition, foundation removal, material recovery and debris clearance under this subcontract.

Method

How the work was done

We used mechanical demolition to remove the villa structures and their foundations.

Equipment 4 excavators
  • 4 × Tata Hitachi EX-200 LC Prime
Workforce 40+ workers

Demolition support and material handling.

  1. Mobilisation

    Excavators and workers brought to site.

  2. Demolition

    The unfinished RCC villas demolished by machine.

  3. Foundations & sorting

    Foundations removed and recovered materials sorted.

  4. Debris clearance

    Debris loaded and removed to clear the work areas.

Result

27 villas demolished in 4 months

The work went smoothly, with no major problems reported. Demolition, foundation removal and debris clearance were completed in four months.

BCM Demolition Group took all recovered materials as part of the project arrangement.

Work areas cleared

What was removed

27 villasDemolished
FoundationsRemoved
Recovered materialsTaken by BCM
DebrisLoaded and cleared
Video

Site video

Footage from the demolition of the 27 villas.

Animated site footage from BCM Demolition Group’s demolition of 27 unfinished residential villas

01Villa demolition

Demolition, foundation removal and debris clearance by BCM Demolition Group.

FAQs

Common questions

How many villas were demolished?

27 unfinished RCC villas at Dodjala, near Devanahalli International Airport, with a combined built-up area of 63,000 sq ft.

Was BCM the main contractor?

No. Uday Kumar won the demolition work from Ideal Pro and appointed BCM Demolition Group as the subcontractor to carry out the full scope.

What equipment and workforce were used?

Four Tata Hitachi EX-200 LC Prime excavators and more than 40 workers.

How long did it take?

Four months, covering the demolition, foundation removal and debris clearance.

Who kept the recovered materials?

BCM Demolition Group took all recovered materials as part of the project arrangement.

error: Content is protected !!
Scroll to Top